105 East 37th Street, Richmond
E&E Enterprise LLC · installed September 24, 2026 · the overview project sheet, at a glance
Project cost
$8,756.00
Total cost $3,417.03 · ganancia $5,338.97 — as the overview sheet computes it.
Materials
$1,192.29
2 receipts
Labor
$1,060.00
6 person-days
Disposables
$289.14
crew supplies
Commission
$875.60
Jorge 10%
Collected
$6,931.00
of $8,756.00
Balance due
$1,825.00
invoice #0007
The money — the overview's own total row
Cost project$8,756.00
Materials$1,192.29
Disposables$289.14
Subcontractor$0.00
Labor$1,060.00
Commission$875.60
Total cost$3,417.03
Ganancia$5,338.97
Payment
Paid $6,931.00 of $8,756.00 — invoice
#000779.2%
Balance due
$1,825.00
status: partial
| 2026-09-22 | Plastiq TD4W8BF — 50% deposit, Invoice 0007 | $2,553.00 |
| 2026-09-29 | Plastiq AJCZ298 - Change Work Order 1 deposit, Invoice 0007 | $1,825.00 |
| 2026-09-29 | Plastiq Q6MIWGV — final payment, Invoice 0007 | $2,553.00 |
Show the invoice lines
| Line | Qty | Cost | Total |
|---|
| Remove Joist | 12 | $212.75 | $2,553.00 |
| Joist Install | 12 | $212.75 | $2,553.00 |
| Subfloor Replace | 192 | $14.00 | $2,688.00 |
| Clean Up & Debris Removal | 800 | $1.00 | $800.00 |
| 6 mil Vapor Barrier | 800 | $1.52 | $1,216.00 |
| Insulation Install | 800 | $1.75 | $1,400.00 |
| Customer Discount | 1 | $-2,454.00 | $-2,454.00 |
Materials — the receipts
Materials total$1,192.29
Labor — the crew on this job
Valerio $200.00/day × 2 = $400.00Santiago $200.00/day × 2 = $400.00Luis $130.00/day × 2 = $260.00
6 person-days · crew cost$1,060.00
Disposables — what the crew used
Trash 4 Mil 6.00 days × $12.19$73.14
Trajes 6.00 days × $3.35$20.10
Pares Guantes 6.00 days × $1.59$9.54
Mascarillas 6.00 days × $2.82$16.92
Pilas 6.00 days × $1.24$7.44
GAS 6.00 days × $27.00$162.00
Disposables total$289.14
Commission
Sales repJorge
Cost project$8,756.00
Rate10%
Commission$875.60
Subcontractor
Subcontractors on this job$0.00